Launch of UK’s ‘largest AI supercomputer’ delayed by power supply problems
The UK's planned "largest AI supercomputer" datacentre in Loughton, Essex, faces significant delays, potentially pushing its launch from next year into the mid-2030s. Nscale, the startup behind the project, is encountering power supply problems, with UK Power Networks reportedly unable to provide sufficient electricity until the early to mid-2030s.

Briefing Summary
AI-generatedThe UK's planned "largest AI supercomputer" datacentre in Loughton, Essex, faces significant delays, potentially pushing its launch from next year into the mid-2030s. Nscale, the startup behind the project, is encountering power supply problems, with UK Power Networks reportedly unable to provide sufficient electricity until the early to mid-2030s. This delay highlights broader issues in datacentre development, as the energy regulator Ofgem has noted a substantial backlog of datacentres seeking electricity connections. The Loughton site requires 90MW of capacity, a demand that necessitates upgrades to the wider national electricity transmission network. Nscale is exploring on-site power generation and ways to expedite the connection process.
Article analysis
Model · rule-basedKey claims
5 extractedThe Loughton site requires up to 90MW of capacity, equivalent to the energy consumption of approximately 315,000 homes.
Ofgem warns of a 'logjam' in electricity connection applications, with 315 datacentres queueing for 73GW of demand.
The project, announced in 2025 as the country’s largest AI supercomputer, was initially planned for a 2027 launch.
UK’s largest AI supercomputer project in Loughton, Essex, faces delays due to power supply problems.
UK Power Networks has informed Nscale that the local grid cannot supply sufficient power until the early to mid-2030s.