News/Google told to halt work on datacentres in Finland over envi…
NSR-2026-1006-116842News Report·EN·Environmental

Google told to halt work on datacentres in Finland over environmental concerns

Google has been ordered by the Finnish Licensing and Supervision Authority (LVV) to temporarily halt preparatory work on two datacentre construction sites in Muhos and Kajaani, Finland. This order stems from the company's failure to conduct necessary environmental impact assessments (EIAs) before commencing significant site alterations, including extensive logging and topsoil removal.

Miranda Bryant Nordic correspondentThe Guardian - World NewsFiled 2026-10-06 · 18:02 GMTLean · Center-LeftRead · 2 min
Google told to halt work on datacentres in Finland over environmental concerns
The Guardian - World NewsFIG 01
Reading time
2min
Word count
450words
Sources cited
4cited
Entities identified
11entities
Quality score
100%
§ 01

Briefing Summary

AI-generated
NEWSAR · AI

Google has been ordered by the Finnish Licensing and Supervision Authority (LVV) to temporarily halt preparatory work on two datacentre construction sites in Muhos and Kajaani, Finland. This order stems from the company's failure to conduct necessary environmental impact assessments (EIAs) before commencing significant site alterations, including extensive logging and topsoil removal. The LVV stated these actions change the environment and impact assessment is crucial. Google has been given until October 23rd to suspend these measures and must submit a written explanation. The company acknowledged falling short of its standards and stated it would follow the LVV's guidance, while also highlighting its existing nature surveys and biodiversity plans. Environmental groups have criticized the extensive deforestation, suggesting it points to a systemic issue driven by the high demand for datacentres.

Confidence 0.90Sources 4Claims 5Entities 11
§ 02

Article analysis

Model · rule-based
Framing
Environmental
Legal & Judicial
Tone
Measured
AI-assessed
CalmNeutralAlarmist
Factuality
0.80 / 1.00
Factual
LowHigh
Sources cited
4
Well sourced
FewMany
§ 03

Key claims

5 extracted
01

Malpractice across two sites appears to be a 'systemic problem' due to companies speeding up processes.

quoteTapani Veistola (Finnish Association for Nature Conservation)
Confidence
1.00
02

Google stated they 'acted in good faith under the Forestry Act' and are advancing landscaping and biodiversity plans.

quoteGoogle
Confidence
1.00
03

The Finnish Association for Nature Conservation blames oversights on the 'overheated' market for new datacentres.

quoteFinnish Association for Nature Conservation
Confidence
1.00
04

Google's subsidiary felled 330 hectares of forest in Muhos without completing an environmental impact assessment.

factualTuike Finland Oy (Google's representative)
Confidence
1.00
05

Google ordered to halt datacentre construction in Finland due to environmental impact assessment failures.

factualFinnish Licensing and Supervision Authority (LVV)
Confidence
1.00
§ 04

Full report

2 min read · 450 words
Google has been ordered to temporarily stop work on two Datacentres in Finland after failing to do the necessary environmental impact assessments on its construction sites.The planned Datacentres in Muhos and Kajanni are part of a €13bn (£11bn) project across multiple sites in northern Finland by the technology company amid huge demand for space to house online infrastructure.It comes after it emerged that Finland-oy" class="entity-link entity-organization" data-entity-id="214365" data-entity-type="organization">Tuike Finland Oy, the company representing Google, had felled 330 hectares (815 acres) of forest in Muhos without completing an Environmental Impact Assessment (EIA).In Kajaani, the company has reportedly been logging across just under 200 hectares (494 acres) of land.The Finnish Association for Nature Conservation said the sites had been reduced to “sand”, blaming the oversights on the “overheated” market for new Datacentres.On Tuesday, the Finnish Licensing and Supervision Authority (LVV) said it had issued a notice to the company to “immediately suspend” – by 23 October at the latest – “preparatory measures that significantly change the environment” of the two sites until the Environmental Impact Assessment had been completed. Google has until next Wednesday to submit a written explanation.The EIA is ongoing and expected to be completed later this year. But Google has gone ahead with “extensive preparatory measures”, including removing trees, stripping topsoil and constructing site roads, LVV said.Tommi Muilu, the head of the environmental department at LVV, said: “In our opinion, the measures in question will change the environment and cause impacts, the identification and assessment of which are among the key objectives of the EIA procedure.”skip past newsletter promotionafter newsletter promotionIf Google does not comply, LVV said it would consider enforcement proceedings and a fine.In response, Google said in a statement “we understand the concerns” and that it had “fallen short of our own high standards”.The company added: “We will study the LVV’s findings and follow their guidance. We acted in good faith under the Forestry Act, and ran nature surveys and put in place measures to protect high-value areas. As we continue our long-term work in the region, we are advancing our landscaping and biodiversity plans, which include tree planting across 130 hectares (321 acres) at Muhos.”Tapani Veistola, the chief operating officer at the Finnish Association for Nature Conservation, said the malpractice across two sites appeared to be a “systemic problem”. The site at Muhos, he said, was “not a forest any more. It is a sand area.”One of the reasons behind it, he said, was the enormous demand to build Datacentres in Finland, which is leading companies to work as fast as possible and overwhelming small municipalities.“The main reason behind everything is the overheated market situation that makes companies speed up processes so much. Also a lack of expertise in municipalities.”
§ 05

Entities

11 identified
§ 06

Keywords & salience

10 terms
environmental impact assessment
1.00
datacentres
0.90
google
0.80
finland
0.70
environmental concerns
0.70
construction sites
0.60
finnish association for nature conservation
0.50
forest
0.50
preparatory measures
0.40
biodiversity plans
0.40
§ 07

Topic connections

Interactive graph
Network visualization showing 51 related topics
View Full Graph
Person Organization Location Event|Click node to navigate|Edge numbers = shared articles