US court rejects Trump’s emergency order keeping Michigan coal plant open
A federal appeals court has ruled that the US Energy Department exceeded its authority by ordering the JH Campbell Generating Plant in Michigan to remain open beyond its planned retirement. The US Court of Appeals for the District of Columbia Circuit unanimously determined that no emergency justified keeping the 64-year-old coal plant online. Energy Secretary Chris Wright had invoked emergency powers, citing the need for reliable electricity and citing increased demand from AI and data centers. The court found the emergency provision of the Federal Power Act was intended for narrow, last-resort situations requiring immediate action. The plant's continued operation, costing millions, was described as disruptive, reversing a long-planned retirement.